To facilitate major renovation works to the glass roof in the main great hall, all the internal upper level balcony lighting needed carefully removing and storing.

Temporary lighting was then installed on internal scaffolding to illuminate the upper level balcony and corridors.

As part of these works, the emergency lighting required relocating. Once complete, all the original light fittings were thoroughly serviced, cleaned and reinstalled.

Given the heights involved and the limited access, an in-depth health and safety risk assessment & method statement was carried out before the works commenced.